The environment of under floor heating system is very
complex, requiring a high thermal conductivity and dimensional stability of the wood
flooring. To ensure a better heat conduction and avoid flooring deformation ,
the thickness should not be more than 8mm for laminate flooring And the other
floorings with thickness more than 8mm, such as hardwood flooring, Bamboo
flooring, engineered wood flooring and laminate flooring are not suitable for under
heating system for the occasion.
Requirements before installation
1. Before the installation, the under heating
system must be tested for the heating water, with the water temperature at
least 50 degrees centigrade, and the underfloor heating system is working
properly, and the system keeps the water temperature more than 12 hours. Makre
sure that there is no leakage before installing the wood flooring on the system.
2 The construction method of destroying the ground surface is not allowed, as this kind of method will undermine the cooling coil of the heating system
3 If the construction is at winter in cold areas, the wood flooring should be kept with open boxed in the field for more than 12 hours in advance, to make the flooring adapt to variations in temperature to avoid the deformation of flooring boards.
4 Before installation, the ground surface should be checked wither it is flat, dry, clean. Make sure the doors and windows are complete, there is no leaking from relevant facilities. In the end, pls check the distance between the door and the ground is enough or not
5 Lay the Special underlayer neatly on the ground, and seal the joints of the underlayers with adhesive tape.
6 Regarding the
laying direction of the flooring, the direction of the long-side flooring board
should be consistent with the room
lighting. During installation, the grooves of the long-side floor in the first
row should be faced to the wall, with wood wedges between the floor and walls and with a floor expansion gap about 8-12mm.The
flooring boards should be staggered between rows and rows for installation and the
dislocation distance should be more than 20 cm.
7 When laying
the flooring, pls pay great attention at all times to the height difference of
the surface, cracks and other defects. Make sure the flooring boards laid are
qualified before gluing the joints and immediately remove residual glue on board.
8 No walking on
the flooring within 12 hours after installation, other subcequent activities of
construction should be carried out after 24 hours.
9 if floor
laying is longer than 8M, or at the joining between rooms , the wood floorings shall be cut off to leave an
expansion gap about 8-12mm, which needs a T profile as connection to reduce the
floor arching.
Baseboard installation
When you install the wood skirting, the
expansion joints should be covered.
Attentions:
1 When decorating the house, we shall pay attention
to the under floor heating system: no legless furniture to avoid wood flooring's local
deformation caused by poor cooling.
2 For the first operation of under heating
system or the restarting after a long time, keep slowl heating speed
(recommended heating rate is 1 c/h) to prevent heating up too fast which could cause
cracking of the wood flooring and twisting. At the same time, pls keep the floor dry.
3 when the indoor air is dry, indoor
humidity should be adjusted.